To modify a shift you must first choose the schedule the shift is in.


1.  Access the schedule you want to work with via Manage Scheduling - Schedules or from the Manager's dashboard under Your Current Schedules.  Choose the schedule by clicking its VSB icon on the listing page 

2.  Each time you access a schedule you are sent to the Shift tab on the VSB.  This is where all shifts are created.


Change the start time:

    1.  Click on the colour band at the top of the shift and hold down your left mouse button then drag the shift to the new start time.  The end time will most likely need to be changed due to this movement.


Change the end time:

    2.  Hover your mouse over the bottom of the shift your mouse arrow will turn into a double arrow (top and bottom arrow) click and hold down left button on mouse then drag the shift up to reduce the length of the shift or down to increase the length of shift.